The “Head Office of Vietnam Electric Equipment CompanyProject” is constructed in a land of 1.937m2, 22 storeys, 03 basements, total construction slab area is 18.289m2 (not yet included basement slab), planed to be completed in 6/2013.
The Project is invested by Vietnam Electric Equipment Company. The Construction Contractor is Lac Hong Jsc.,.
M/S Consultancy and Investment CONINCO Jsc. has been selected to implement the work of Consultant Supervision for this Project.